
Contents: History of the South Western | The Manukau Extension | Completed Images | Construction Images | Merging issues at the Southern The South Western Motorway & Western Ring The South Western Motorway (SH20) has been under construction to connect to motorways in the north and south since the 1970s. From 1997 to now the motorway has been extended in both directions. The main purpose of the South Western Motorway is to provide connections to the Auckland Airport. Eventually when connected to existing motorways the motorway will be an alternative to the Southern motorway - completing the currently under construction Western Ring Motorway Network. The first section of the South Western Motorway started construction in late 1977, the section was only a short approach to the old Mangere bridge bypassing the busy Onehunga area. The northbound Mangere Bridge after a very long construction process was completed in March 1983. It connected the already used Onehunga bypass to the newly completed crossing to create a total section between Neilson Street and Coronation Road of 1.8km. Recent activity: This project is one of the projects of the Western Ring Route. The Western Ring Route will offer a much needed alternative to the congested Northern and Southern Motorways. There are seven projects on this network with five now completed, the Waterview Connection and North Western Widening projects are yet to be completed. Fully Completed: December 2010. $240m. The new section of motorway is 4.5km in length and features five overbridges and five interchanges including the major interchange with the Southern Motorway. Nesdale, Liverpool and Cavendish Drives will be widened to four lanes - offering easier access to main roads in Manukau and offering an improved connection for Roscommon Road to Southern Motorway traffic heading northbound. Southbound lanes opened on Sunday the 29th of August 2010 and westbound lanes opened on Monday the 27th of September 2010. To see a larger version of the map below click here. |
|
The southbound lanes opened on Sunday the 29th of August 2010 and the westbound lanes opened on Monday the 27th of September 2010. The westbound Roscommon Road to Puhinui Road connection, the Wiri Station Road extension (to Lambie Drive), and the link from southbound Southern will not open until December 2010. Below are completed images of the motorway extension.
|
|
The project commenced construction in 2006, and is yet to be completed by December 2010. Below are construction images of the motorway extension.
|
||||||||||||||||||||||||||
Merging issues at the Southern Since the opening of the Manukau Extension significant and problematic congestion has been created on the Southern Motorway. This occurs in the afternoon peak period. Before the motorway opened traffic usually banked up between East Tamaki and the Redoubt Road off-ramp. Now congestion occurs between Highbrook and Takanini. Not only does the congestion exist, it also lasts longer. Congestion used to occur between 5pm and 6.15pm, now it exists between 4pm and 6.40pm every weekday. Despite the obvious reason for the congestion to occur (extra traffic), there are two reasons as to why congestion has occurred in the area:
What should have been completed in the area is this: The South Western enters on their own lane which runs for about two kilometres to end at Hill Road (as an auxiliary lane[?]), all traffic from the South Western that is continuing south moves into the second lane, which has Redoubt Road traffic on it. The second lane continues all the way to at least Takanini as three lanes total. Like this:
Ramp Signalling should not exist on the South Western motorway merge with the Southern; it will defeat the purpose of providing an alternative to the southern motorway by possibly jeopardising gained time. Ramp Signalling should exist at the Redoubt Road on-ramp (as it does), which means the second lane (from the above scenario) is free for South Western traffic to move into before it ends at Hill Road. Currently a third lane extension all the way to Papakura is proposed but funding has not yet been allocated for it. Ramp Signalling has been installed on three lanes of the on-ramp and has lessened the extent of the congestion on the Southern and also lessened the extent of congestion that the temporary lane drop caused on the South Western. Ramp Signalling here should be a temporary measure. The merge at Manukau is a disaster, it should be fixed and fast. Aucklanders do not want motorways that make matters worse. This has been written by the website's author Benjamin Paul. This website is not run by the NZTA or government. Click here for about. |
This is a Western Ring Motorway - adding to the Western Ring Motorway Network << North: Mangere Bridge and Surrounding Widening South Western Motorway Projects: Mangere Bridge & Surrounding Widening | The Waterview Connection | The Mt Roskill Extension |
© 2011 AucklandMotorways.co.nz; Benjamin John Paul. Design by Tridium.