Newmarket Viaduct Replacement Project
Under construction since June 2009 | $215m |
Completion: Late 2012 (total of 49 months). Full timeline.

The above graphic is an animated GIF and should play automatically through the five stages.
The Newmarket Viaduct Replacement is replacing the existing Newmarket Viaduct by constructing two new viaducts (one in each direction). The new southbound viaduct being east of the existing southbound viaduct and the new northbound viaduct in place of the existing southbound one. This equals the staged demolition of the existing viaduct and the new viaduct being around 20m east of the existing viaduct footprint.
The current stage is the demolition of the existing northbound viaduct. Once that is finished the project is complete. All traffic is now using the new viaduct.
Construction method
The new Newmarket Viaduct is constructed using a pre-cast segmental balanced cantilever method. This is basically a balanced cantilever method with each (girder) section built (cured, pre-stressed) off-site then installed onsite in a section by section basis.
A standard balanced cantilever method is where piers are constructed then girder sections are built on each side of the pier until they join to the other piers. They are constructed in unison from one central point outwards. This method was used on the Upper Harbour Motorway Greenhithe bridge construction and illustrated below:

With the Newmarket Viaduct replacement, a segmental balanced cantilever method does not require construction of the girders at site, the girders are constructed and pre-cast in East Tamaki (this allows for less disruption). The 'big blue' horizontal crane lowers each girder section on the ends of the bridge deck. Sections are still added in balance (unison from the middle/pier) until they meet other pier sections. This method does allow the crane to start at one end and finish at the other, without sections needing to be built from piers all at once.

A 'girder' is a box like pre-cast concrete structure, the top of the girder is the bridge deck and the hollow section underneath is where the strength lies. In this case the girders are built off-site and brought to Newmarket when ready to add to the structure. The overhead launching crane lowers the girder into position where it is glued (with an extremely strong epoxy) and fixed to the other girders (or pier girder) with tendons, cables and tongue & groove style keys. This is illustrated below:
Each girder weighs around 80 tonnes and all 498 of them are different and made to fit for the location intended.
Note: Certain girder may or may not contain the joint assistants mentioned above and all illustrations are provided as a indicative guide to illustrate the construction.